Lesco New Connection Procedure Online

Wondering how to get a new electricity connection in Pakistan? The WAPDA has simplified the process through its online Electricity New Connection (ENC) system. Here’s a breakdown of the steps to apply for a Lesco new connection:

Lesco New Connection

Fill Online Application Form

  1. Visit ENC Website: Start by visiting the ENC website and clicking on the “Apply” button.
  2. Select Lesco: Choose Lesco as your distribution company.
  3. Enter Reference Number: Enter your neighbor’s 14-digit reference number; it will automatically locate your subdivision.
  4. Select Category and Connection Type: Choose your category (e.g., load up to 15kW for home users) and connection type (e.g., Domestic for home users).
  5. Provide Applicant Details: Fill in your particulars, including Applicant Name, Father Name, CNIC number, Present address, and Mobile numbers.
  6. Submit Application: Agree to the terms, click “Submit,” and note down the provided tracking ID for your Lesco new connection.

Documents Required for New Connection Lesco

To complete your application, you’ll need to upload the following documents:

  • Property document image
  • Attested CNIC Copy of Applicant
  • Attested CNIC Copy of Witness
  • Neighbor Bill Copy
  • Wiring contractors test report
  • Undertaking from Applicant

Printing and Submitting the Application

  1. Print Application: Click on the print button, enter your tracking ID, and print your application form.
  2. Submit to Lesco Office: Attach the necessary documents and submit the hard copy to the nearest Lesco office.

Supported Documents for Electricity New Connection

Time Frames for New Connections

In adherence to the OS3-NEPRA guideline, a distribution company is obligated to ensure that electric power service reaches a minimum of 95% of new connections for eligible consumers. These criteria, as per the Consumer Eligibility Criteria defined by the Authority under section 21(2)(b) of the Nepra Act, come with specified timeframes for each category, beginning from the date of application for a new connection.

DescriptionVoltage LevelLoad (kW)Timeframe (Days)
For residential connections up to 400V and load up to 15 kWUp to 400VUp to 1530
For residential connections up to 400V, load > 15 kW but ≤ 70 kWUp to 400V> 15, ≤ 7053
For residential connections up to 400V, load > 70 kW but ≤ 500 kWUp to 400V> 70, ≤ 50073
For connections at higher voltage levels (11 or 33 kV), load > 500 kW11 or 33 kV> 500, ≤ 5000106
For connections at voltage Level 66 kV and above, all types of loads66 kV and aboveAny496

Explanation: The timeframe is calculated from the date of the application’s registration until the consumer is successfully provided with the connection. Importantly, the standard time limits exclude any duration beyond the control of the distribution company.

Change Connection Name/Tariff/Load Process for Lesco Users

If you need to change your Lesco electricity meter ownership, tariff, or load, here’s a straightforward process:

Change Application Type

  1. Visit ENC Official Site: Go to the ENC website and click on the “Change” option.
  2. Select Application Type: Choose the change options relevant to your needs, such as Change of Name, Tariff, and Load.
  3. Fill Applicant Particulars: Provide details like Reference number, CNIC, Mobile Number, and Current Name.
  4. Additional Details for Each Change: If changing name, fill in Current and New Name. If changing tariff, select old and new tariffs. If changing the load, select the type and specify the load changes.

Documents Required for Change of Name/Tariff/Load

Upload the following documents during the application:

  • Attested CNIC Copy of Applicant
  • Applicant Electricity Bill Copy
  • Proof of ownership

Submitting and Printing the Application

  1. Submit Application: Submit the application and note the tracking ID for future reference.
  2. Print Form: Click on the “Print form” option, select Lesco as the company, and print the application.
  3. Submit to Lesco Office: Attach necessary documents and submit the hard copy to the designated Lesco office.

Lesco New Connection Tracking

Curious about your Lesco new connection application status or the changes you’ve requested? Follow these simple steps:

  1. Visit the ENC Site: Go to www.enc.com.pk.
  2. Click on Track: On the ENC page, click “Track.”
  3. Select Application Type: Choose “New Connection” or “Change of Name/Tariff/Load.”
  4. Choose Lesco: Select Lesco from the dropdown.
  5. Enter Tracking ID: Input your tracking ID and submit.

Lesco New Connection Demand Notice (Print, Pay, and Upload)

After verification, a demand notice will be issued. Here’s how to handle it:

  1. Download Demand Notice: Visit the ENC website, click “Print DN,” choose Lesco, and enter the tracking ID.
  2. Print and Pay: Print the demand notice, pay the fee at the concerned bank (like Punjab Bank), and upload the paid demand notice online.
  3. Verification and Changes: Once verified, your requested changes will take effect.

Lesco New Connection Bill Check Online

When you’re all set for your new Lesco connection, waiting for the bill is part of the process. Usually, it takes 2 to 3 months. But here’s the good news – you can check your new connection bill online!

All you need is your connection reference number. Get this number from your demand notice, the paper you got when you applied. Look for the 13-digit reference number on it, and you’re ready to check and manage your new connection bill online hassle-free. It’s an easy way to keep track of your electricity expenses.

Reference Number Check for LESCO New Connection

Lesco New Meter Connection Fee

The Lesco New Meter Connection Fees can vary based on your local area or society. As of the recent demand notice issued on December 1, 2023, the cost was approximately 9400 PKR. It’s important to note that the price may change depending on your specific location. For a more accurate understanding of the fees and to get a precise quote, it is recommended to contact your local Lesco office.

Provide them with your bill as a reference so that they can assess your situation and provide you with the exact cost for the demand notice. This method applies not only to residential connections but also to commercial meter new connections. Reach out to your area Lesco office for personalized assistance and to obtain the most up-to-date information on Lesco new connection demand notice fee.

To Sum Up

Now you have the key information to navigate the Lesco new connection process. Apply online or visit your nearest Lesco office to initiate the process. Track your application easily and stay informed about any changes or demands. The ENC system ensures a streamlined approach, making Lesco new connections convenient and efficient.

Remember, this information may take 2 to 3 months to arrive at your meter. For any additional queries or clarifications, don’t hesitate to reach out to Lesco or visit the ENC website.

FAQs

Lesco Bill cr Meaning

CR” on a LESCO bill stands for “Credit,” which indicates that there is an advance payment or credit balance on the account. This means that the customer has made a payment in advance, and the credited amount will be deducted from the next month’s bill.
It’s a common practice in utility billing systems to show credit balances or advance payments on bills to reflect the prepayment made by the consumer.

What is Consumer Number on lesco bill

The consumer number on a LESCO (Lahore Electric Supply Company) bill is a unique identification number assigned to each electricity consumer or account. It serves as a reference to identify and track the billing and usage information associated with a specific connection.
The consumer number is typically used for administrative purposes and helps the utility company and the consumer manage and track electricity usage, billing, and other related services.